Project Highlights – September 2021

  • Beck & Bellucci (B&B) is looking to complete the installation of the King Pile retaining wall along US Route 202.
  • B&B subcontractor, Weaver Bros, is going to continue removal of the temporary access road and install large rocks along the face of the King Pile Wall to prevent scouring by the river.
  • B&B is constructing sidewalks on the southern end of US Route 202.
  • B&B will begin work around the transcript dam by driving steel sheeting to create a water tight work space.
  • B&B will continue constructing and installing formwork for the concrete arch.